An FSP appoints a representative who does not yet meet the full competence requirements. What arrangement makes this permissible?
RE5 practice question with a worked answer. This is one of hundreds of FSCA RE5 questions in the RegulatoryExams question bank.
- a) The FSP waives the competence requirements permanently.
- b) The product supplier takes over responsibility for the representative.
- c) The representative works under supervision while completing the competence requirements within the prescribed periods.Correct
- d) The representative simply signs a declaration that they will study one day.
Why this is the answer
A not-yet-fully-competent representative may be appointed if they work under supervision and complete the qualification, regulatory exam and product training within the prescribed timeframes. The requirements cannot be waived away by a declaration.
Want to test yourself on 700+ more questions like this?
Start your free RE5 simulator today — timed mock exams, full answer explanations and cloud-synced progress tracking.
More Fit & Proper questions
- Refilwe was first appointed as a representative for a Tier 1 product on 1 February 2021…
- When applying to be a representative, Mpho leaves out the fact that a professional body…
- Vuyo must complete 6 CPD hours per cycle. He completes 4 accredited hours in July 2024…
- An insurer materially changes the benefits and exclusions of a policy that Kabelo has s…